Guangdong built a special vehicle relocation project


1. Reason and time for relocation

Since the current factory area was built in 1987, with the development of urban construction, the current factory site has been located in a residential area in Kaiping City, which has been planned by the Kaiping Municipal Government as a development area for commercial and residential purposes. The living environment is affected, and the company's factory space is currently small, which is limited by the layout, resulting in unreasonable production logistics, and the production capacity and production cost are difficult to meet the needs of market competition. To sum up, due to the current production layout, production area And the limitation of production equipment, the production capacity of the factory is difficult to break through, and the management level is difficult to improve. All these factors lead to a large gap between the production capacity of the company's products and the market demand. It is urgent to improve the production capacity and manufacturing level through overall relocation to meet the market demand. At the same time, it also cooperates with the overall urban development plan of Kaiping City and creates a good living and living environment for the residents around the current factory area. The company decided to strive to complete the design work and start construction in 2014 or early 2015, and plans to put it into production next year.

2. Preliminary planning

On March 20, 2014, Guangdong Jiancheng Special Vehicle Project held its first regular meeting and established a project leading group and office. According to the project planning and the work arrangement of the project office, joint venture cooperation and equity financing structure design were carried out for project joint venture cooperation, relocation and reconstruction work. , Equity Incentive Plan (MBO), asset evaluation and audit, research and design of process layout, land purchase policy and pre-purchased land area and location, and multiple negotiations with joint venture partners, etc. The preliminary work of the project is the initial blueprint for the company's relocation project. .

As early as 2010, the company had signed a letter of intent for investment with the Management Committee of Kaiping City Cuishan Lake Industrial Transfer Industrial Park; after many consultations, on June 12 this year, the company's chairman Miao Kongyou and the Management Committee of Cuishan Lake Industrial Park formally signed an investment agreement. In the contract, it was decided that the new factory would be built in Cuishan Lake Industrial Park, and its specific location was determined.

Dangerous goods transport vehicle